A Method to the Madness: The Pitfalls of the “As-Planned vs. As-Built” Forensic Scheduling Analysis

October 25, 2023

Juan J. Miranda

share this page

A Method to the Madness: The Pitfalls of the “As-Planned vs. As-Built” Forensic Scheduling Analysis

When selecting or defending against a litigation scheduling expert, a construction law practitioner must understand the scheduling expert’s methodology employed to evaluate project delays and the allocation of the fault for those delays. There are several forensic methods available, but courts have consistently viewed the “As-Planned vs. As-Built” (or “APAB”) methodology as the least reliable. A practitioner must be able to spot and criticize the use of APAB when used to evaluate scheduling delays on large and complex projects that deviate significantly from the project baseline schedules.

The APAB’s unreliability is based on its inherent limitations, as recognized and defined by AACE International Recommended Practice No. 29R-03 Forensic Scheduling Analysis (the “Recommended Practice”). APAB is simply an observational basic method that “consists of analyzing the [baseline] schedule by examining a schedule, by itself or in comparison with another, without the analyst making any changes to the schedule to simulate any specific scenario[1].” The Recommended Practice thus classifies APAB “as gross as opposed to periodic because the analysis is performed on the entire project against a single baseline or other planned schedule rather than in periodic segments.” In other words, APAB does not account for actual events and activities that occur during the construction of a project.

The Recommended Practice stresses that observational methods, like APAB, are applicable “to relatively simple projects and should not be used for long duration projects or where there are significant changes between the original planned work scope and the final as-built scope.” APAB  “is useful only for simple projects where the sequence of work did not vary significantly from the baseline schedule.” In short,  APAB  is essentially “a comparison of an as-built schedule to just one set of as-planned network logic,” and therefore it should not be used to evaluate delays on large and complex construction projects.

Courts disfavor the use of APAB for proving delay and fault because it assumes only one party is responsible for all of the project’s delay[2]. By using the APAB method, “a party simply subtracts the planned duration of a project from the actual duration of the project to identify the total delay to the work[3],” but without any analysis of the delay periods or proper efforts to ascertain concurrent or overlapping delays caused by others or other events. That is, the “cause” of the delay is assumed without proof, thus avoiding or bypassing a claimant’s burden to prove causation, by ignoring other causes, affecting the actual sequence of work, such as weather and subcontractor productivity. Because of the methodological flaws and limitations, some courts have rejected APAB entirely[4].

For example, in Mega Construction Co., Inc. v. United States, 29 Fed. Cl. 396 (1993), the U.S. Postal Service terminated a $2 million fixed-price contract for cause due to the general contractor’s failure to comply with directives and abandonment of the work. In rejecting the contractor’s use of APAB to calculate delay damages, the court levied the following criticism:

The court does not view plaintiff's incomprehensible and suspect bar charts as demonstrating the critical path of the project, and no other evidence revealed the interdependence of the various activities of the project. The bar charts do not show the critical path, and thus do not permit a critical path analysis. At best, there may have been concurrent delay by both parties, but plaintiff made no attempt to apportion such delay[5].

***

Without a critical path analysis, the court cannot exclude the possibility that the contractor caused concurrent delay on the project. Plaintiff's charts are not sufficient to prove allocation between the parties or attribution to defendant. The court cannot rely on assertions of a contractor, not supported by a critical path analysis of the project, to award critical path delay costs. Neither did plaintiff show by a preponderance of the evidence that the claimed delays were of an unreasonable length and that any of the claimed work item delays caused material damage. This was insufficient to sustain plaintiff's contention that defendant's actions delayed the completion of the project by 272 days, or for any other quantifiable period of time. Plaintiff failed to prove entitlement to an equitable adjustment for delay to any work item, or project delay[6].

The court rejected APAB as unreliable because it did not account for the interdependence of construction activities or segregate key details needed to allocate responsibility for the delay and determine its precise duration.

National surveys evaluating the acceptability percentage of different scheduling delay methods also reflect the courts’ skepticism surrounding the use of APAB. APAB has been accepted in only 14% of the 57 cases surveyed, while more reliable methods have been accepted by courts up to 85% of the time[7].

NUMBER OF CASES ACCEPTED/NOT ACCEPTED/REJECTED % ACCEPTED V NOT ACCEPTED OR REJECTED % NOT ACCEPTED OR REJECTED V ACCEPTED
Adjusted TIA 20 85% 15%
Windows 20 50% 50%
Prospective TIA 12 50% 50%
Windows wide periods 3 0% 100%
Collapsed As-Built 11 27% 73%
As-Built Critical Path 26 15% 85%
Impacted As-Planned 24 14% 83%
As-Planned vs. As-built 57 14% 86%
Total 173

In at least two studies, the APAB Method came in dead last in comparison to other methodologies[8].

Although the APAB Method may at times be useful for evaluating delays on small projects that proceed in the sequence outlined in the baseline schedules, a practitioner should be highly skeptical of using the APAB Method on large and complex projects, particularly when there are significant deviations from the baseline schedules. When faced with evaluating delays on large projects, a practitioner and his expert should consider using a more robust methodology that considers concurrent delays, evaluates each parties’ fault for the delays, and requires the expert to evaluate project documents such as daily field reports, supervisor reports, meeting minutes, and photographs. In sum, a practitioner should always ensure that his expert, or that of his opponent, is employing a method that accurately reflects the reality of what occurred on the construction project.


[1] AACE International Recommended Practice No. 29R-03 Forensic Schedule Analysis.

[2] See, e.g., J. Wm. Foley, Inc. v. United Illuminating Co., 2013 Conn. Super. LEXIS 2028, 2013 WL 5422454, at *16 (Conn. Super. Ct. 2013) (calculating a total delay period and assigning responsibility to the defendant is "insufficient and of virtually no value").

[3] W. Stephen Dale & Robert M. D’Onofrio, Construction Schedule Delays §11.1 (2021).

[4] See, e.g., K-Con Bldg. Sys., Inc. v. U.S., 131 Fed. Cl. 275 (2017)(rejecting the APAB approach after finding that the method did not reflect that plaintiff did not actually perform in accordance with the schedule and did not reflect the reality of what occurred on the project).

[5] Id. at 435(internal citations omitted).

[6] Id. (internal citations omitted).

[7] W. Stephen Dale & Robert M. D’Onofrio, Construction Schedule Delays §12.3 (2021).

[8] Id.; see also, David Arditi & Thanat Pattanakitchamroon, Analysis Methods in Time-Based Claims, 134 No. 4 ASCE J. Const. Eng’g & Mgmt. 242 (Apr. 2008).

Firm Highlights

  • Insight

    No Mercy for Employers in Louisiana Supreme Court’s Recent Magill Decision

    In its recent per curiam opinion, Magill v. Werner Enterprises, Inc. of Nebraska[1], the Louisiana Supreme Court has foreclosed a routine defense strategy to shield employers from direct negligence claims. The high court has extended their 2022 decision in Martin v. Thomas[2], and now allows plaintiffs to pursue direct negligence claims against an employer despite the employer’s stipulation that its employee was in the course-and-scope of employment and caused the accident. Essentially, employers who fail to implement better employment practices will permit plaintiffs to ramp up potential exposure with evidence, if such exists, that heretofore they were routinely barred from introducing at trial. The Supreme Court’s Magill holding should encourage employers to update where needed their policies and procedures pertaining to hiring, training, supervising, and entrusting duties and property to employees, not only for the safety of their employees and customers in this state, but also eliminate employer’s exposure to direct negligence claims. Prior to Martin, a litigation strategy had taken shape where employers stipulated to 1) an employee being in course-and-scope of employment at the time of the accident, 2) that the employee was at fault for the accident being caused, or 3) both. By stipulating these facts, employers were largely able to exclude evidence of any direct negligence on part of the employer and/or narrow the scope of trial to only a contest of the plaintiff’s injuries. The Supreme Court in Martin held that despite an employer admitting their employee was in course and scope when the accident occurred, plaintiffs could pursue direct negligence claims against the employer—as the issue of liability had not been admitted. Accordingly, employers found success by admitting both course and scope and liability—as seen in the Western District of Louisiana’s holding in Ferguson v. Swift Transp. Co. of Arizona[3]. In Ferguson, the defendants stipulated that their employee was acting in course-and-scope at the time of the accident and their employee was 100% at fault for the accident being caused. Due to the employer’s stipulation of fault, Judge Wicks of the Western District of Louisiana held that Martin did not apply and that plaintiffs could not pursue direct negligence claims. In Magill, the Louisiana Supreme Court provided scarce reasoning for their decision. The high court simply affirmed the District Court’s expansion of the holding in Martin and that the employer’s reliance on the Western District’s Ferguson holding was a misapplication of Louisiana law. The Supreme Court also cited the decision in Tardo v. Farrell.[4] where the Fifth Circuit held that even if an employer and employee stipulate to course and scope and fault, those admissions do not eliminate direct-negligence claims because those claims remain separate issues for the trier of fact. The Fifth Circuit notably stated, “the societal decisions as to who actually pays does not change the manner of assessing fault to all parties as required by law.” This statement raises concern, as plaintiffs may now attempt to challenge employer stipulations that historically narrowed trials. The Supreme Court did not explain its reliance on Tardo, so future litigation will likely clarify the decision’s full impact. Under Magill, plaintiffs are permitted to pursue direct negligence claims against the employer despite the employer admitting that their employee was acting in course and scope at the time of the accident and their employee was 100% at fault for the accident being caused. The full effect of the Supreme Court’s decision remains to be seen. In praxis, Magill will permit plaintiffs to put on evidence of direct negligence by an employer in front of a jury who cannot assign fault—as fault has already been stipulated to by the defendants. Employers now face the practical risk that plaintiffs will encourage juries to increase damages as a form of punishment against an employer that admits fault but contests the nature and extent of the plaintiff’s injuries. Employers should use this moment to rigorously review and strengthen policies and procedures related to hiring and training in order to limit exposure when plaintiffs assert direct-negligence claims.  [1] Magill v. Werner Enterprises, Inc. of Nebraska, 2025-00892 (La. 11/12/25) [2] Martin v. Thomas, 21-01490 (La. 6/29/22), 346 So.3d 238 [3] Ferguson v. Swift Transp. Co. of Arizona, 17-1570, 2023 WL 173413 (W.D. La. Jan. 12, 2023) [4] Tardo v. Ferrell, 25-123 (La. App. 5 Cir. 5/28/25), 2025 WL 1516837 (unpublished).
  • Experience

    Burnell Joseph v. Atalco Gramercy, LLC et al., No. 3:23-cv-505, United States District Court for the Middle District of Louisiana

    Bob Kerrigan and Jose Ruiz successfully secured summary judgment dismissal for their client, Velan, Inc., in a complex intentional tort and products liability act involving catastrophic injury. The plaintiff, a precipitation batch tank operator working at the Atalco alumina refinery in Gramercy, Louisiana, suffered severe and debilitating chemical burn injuries to his face, eyes, and body when he was sprayed with caustic liquor while working underneath a tank at the refinery. He claimed that the valve that controlled the flow of liquor into the tank was leaking, which allowed the tank to become filled with liquor after it had been previously verified as empty. He filed suit against Velan, Inc., the manufacturer of the valve that controlled the flow of liquor into the tank, alleging that the valve was unreasonable dangerous in accordance with the Louisiana Products Liability Act. He also filed an intentional tort claim against his employer, Atalco Gramercy, LLC, alleging that Atalco knew the valve was leaking and continued to force employees to work underneath the tank. He claimed that under these conditions, an incident such as his was substantially certain to occur. Following the close of discovery, Velan moved for summary judgment dismissal of the plaintiff’s claims was appropriate because: (1) the plaintiff’s injuries were a result of Atalco’s misuse of the valve; (2) the plaintiff lacked the expert testimony needed to prove his theory of liability under the Louisiana Product’s Liability Act; (3) the Velan valve at issue was not unreasonably dangerous as defined by the Louisiana Products Liability Act; and (4) the plaintiff was unable to prove proximate causation needed to establish his case of liability against Velan. The Hon. Brian Jackson found that under the undisputed facts presented by Velan, summary judgment was appropriate and dismissed the plaintiff’s claims against it, with prejudice.