Recent Changes to Change Orders on Louisiana Public Works Projects

November 9, 2023

Brian S. Schaps

share this page

Recent Changes to Change Orders on Louisiana Public Works Projects

The Louisiana legislature recently amended La. R.S. 38:2212(M) governing change orders on public works projects. A change order is a written amendment to an existing construction contract that alters the work to be performed, the contract sum, and/or the contract time.  A public works project is the erection, construction, alteration, improvement, or repair of any public facility or immovable property owned, used, or leased by a public entity.

The amendment to La. R.S. 38:2212(M) now requires that change orders must include fully documented and itemized costs for labor and equipment included in the change order.

For any change order requiring redesign, the amended law now requires that the redesign shall not take more than 90 days following notification by the contractor to the designer of record, or in the absence of the designer, the public entity, of the discovery of work to be performed by the change order. Extensions of time may be granted by the public entity if necessary for the redesign.

Upon completion of the redesign, the contractor must submit a cost estimate to the designer or the public entity for the change order within 45 days for the redesigned work to be performed under the change order. The public entity has 30 days from the submittal of the change order to negotiate, approve, or reject the contractor's proposed cost estimate of the work. Extensions of time may be granted by mutual agreement or shall be granted as necessary for the public entity to obtain governmental approval.

The prior law had provided that no deviations were allowed in change orders where unit prices were contained in the initial contract. The new amendment now allows for, but does not require, change orders which relate to certain unit price work to be negotiated if notice of the change order work and proposed new pricing is provided within 30 days of the discovery of the work to be performed by change order.

Finally, the contractor shall not be required to provide any schedule updates incorporating a change order until the change order is executed, unless the schedule is needed for evaluation of the proposed change order.

These amendments became effective on August 1, 2023, and the requirements of these amended provisions cannot be waived by contract. 

Firm Highlights

  • Insight

    No Mercy for Employers in Louisiana Supreme Court’s Recent Magill Decision

    In its recent per curiam opinion, Magill v. Werner Enterprises, Inc. of Nebraska[1], the Louisiana Supreme Court has foreclosed a routine defense strategy to shield employers from direct negligence claims. The high court has extended their 2022 decision in Martin v. Thomas[2], and now allows plaintiffs to pursue direct negligence claims against an employer despite the employer’s stipulation that its employee was in the course-and-scope of employment and caused the accident. Essentially, employers who fail to implement better employment practices will permit plaintiffs to ramp up potential exposure with evidence, if such exists, that heretofore they were routinely barred from introducing at trial. The Supreme Court’s Magill holding should encourage employers to update where needed their policies and procedures pertaining to hiring, training, supervising, and entrusting duties and property to employees, not only for the safety of their employees and customers in this state, but also eliminate employer’s exposure to direct negligence claims. Prior to Martin, a litigation strategy had taken shape where employers stipulated to 1) an employee being in course-and-scope of employment at the time of the accident, 2) that the employee was at fault for the accident being caused, or 3) both. By stipulating these facts, employers were largely able to exclude evidence of any direct negligence on part of the employer and/or narrow the scope of trial to only a contest of the plaintiff’s injuries. The Supreme Court in Martin held that despite an employer admitting their employee was in course and scope when the accident occurred, plaintiffs could pursue direct negligence claims against the employer—as the issue of liability had not been admitted. Accordingly, employers found success by admitting both course and scope and liability—as seen in the Western District of Louisiana’s holding in Ferguson v. Swift Transp. Co. of Arizona[3]. In Ferguson, the defendants stipulated that their employee was acting in course-and-scope at the time of the accident and their employee was 100% at fault for the accident being caused. Due to the employer’s stipulation of fault, Judge Wicks of the Western District of Louisiana held that Martin did not apply and that plaintiffs could not pursue direct negligence claims. In Magill, the Louisiana Supreme Court provided scarce reasoning for their decision. The high court simply affirmed the District Court’s expansion of the holding in Martin and that the employer’s reliance on the Western District’s Ferguson holding was a misapplication of Louisiana law. The Supreme Court also cited the decision in Tardo v. Farrell.[4] where the Fifth Circuit held that even if an employer and employee stipulate to course and scope and fault, those admissions do not eliminate direct-negligence claims because those claims remain separate issues for the trier of fact. The Fifth Circuit notably stated, “the societal decisions as to who actually pays does not change the manner of assessing fault to all parties as required by law.” This statement raises concern, as plaintiffs may now attempt to challenge employer stipulations that historically narrowed trials. The Supreme Court did not explain its reliance on Tardo, so future litigation will likely clarify the decision’s full impact. Under Magill, plaintiffs are permitted to pursue direct negligence claims against the employer despite the employer admitting that their employee was acting in course and scope at the time of the accident and their employee was 100% at fault for the accident being caused. The full effect of the Supreme Court’s decision remains to be seen. In praxis, Magill will permit plaintiffs to put on evidence of direct negligence by an employer in front of a jury who cannot assign fault—as fault has already been stipulated to by the defendants. Employers now face the practical risk that plaintiffs will encourage juries to increase damages as a form of punishment against an employer that admits fault but contests the nature and extent of the plaintiff’s injuries. Employers should use this moment to rigorously review and strengthen policies and procedures related to hiring and training in order to limit exposure when plaintiffs assert direct-negligence claims.  [1] Magill v. Werner Enterprises, Inc. of Nebraska, 2025-00892 (La. 11/12/25) [2] Martin v. Thomas, 21-01490 (La. 6/29/22), 346 So.3d 238 [3] Ferguson v. Swift Transp. Co. of Arizona, 17-1570, 2023 WL 173413 (W.D. La. Jan. 12, 2023) [4] Tardo v. Ferrell, 25-123 (La. App. 5 Cir. 5/28/25), 2025 WL 1516837 (unpublished).
  • News

    44 Deutsch Kerrigan Attorneys Recognized by Best Lawyers® in 2027 Edition, Including Two “Lawyer of the Year” Honorees

    Deutsch Kerrigan proudly announces that 44 of our attorneys have been recognized by their peers in the 2027 editions of The Best Lawyers in America® and Best Lawyers: Ones to Watch® in America. This year, 34 Deutsch Kerrigan attorneys were named to The Best Lawyers in America®, with an additional 10 attorneys recognized in Best Lawyers: Ones to Watch® in America. In addition, John Jerry Glas and Kelly E. Theard were each named “Lawyer of the Year” in their respective practice areas—an honor awarded to only one attorney per practice area in each region. John Jerry Glas — Transportation Law, New Orleans Kelly E. Theard — Professional Malpractice Law – Defendants, New Orleans Below is the full list of Deutsch Kerrigan attorneys recognized in the 2027 editions of The Best Lawyers in America® and Best Lawyers: Ones to Watch® in America. 2027 The Best Lawyers in America® Thirty-four Deutsch Kerrigan attorneys were recognized in the 2027 edition of The Best Lawyers in America®: New Orleans, Louisiana Jennifer Adams Litigation - Environmental Product Liability Litigation - Defendants Francis J. Barry, Jr. Admiralty and Maritime Law Product Liability Litigation - Defendants Keith J. Bergeron Construction Law Litigation - Construction Professional Malpractice Law - Defendants Terrence L. Brennan Arbitration Construction Law Litigation - Construction Professional Malpractice Law - Defendants Bertrand M. Cass, Jr. Admiralty and Maritime Law Energy Law Personal Injury Litigation - Defendants Beverly Aloisio DeLaune Commercial Litigation Legal Malpractice Law - Defendants Professional Malpractice Law - Defendants Catherine Filippi Personal Injury Litigation - Defendants John Jerry Glas Insurance Law Mass Tort Litigation / Class Actions - Defendants Personal Injury Litigation - Defendants Transportation Law David Groome, Jr. Litigation - Insurance Personal Injury Litigation - Defendants William C. Harrison, Jr. Aviation Law Mass Tort Litigation / Class Actions - Defendants Personal Injury Litigation - Defendants Product Liability Litigation - Defendants Carl "Chip" Hellmers Medical Malpractice Law - Defendants Karen Holland Professional Malpractice Law - Defendants Duris L. Holmes Banking and Finance Law Bankruptcy and Creditor Debtor Rights / Insolvency and Reorganization Law Business Organizations (including LLCs and Partnerships) Commercial Litigation Litigation - Bankruptcy Joshua G. Keller Insurance Law Litigation - Insurance Personal Injury Litigation - Defendants Ryan D. Kelley Insurance Law Personal Injury Litigation - Defendants Robert E. Kerrigan, Jr. Commercial Litigation Litigation - Environmental Litigation - Insurance Mass Tort Litigation / Class Actions - Defendants Personal Injury Litigation - Defendants Product Liability Litigation - Defendants Charles E. Leche Admiralty and Maritime Law Personal Injury Litigation - Defendants Product Liability Litigation - Defendants Frederic Theodore Le Clercq Employment Law - Management Labor Law - Management Litigation - Labor and Employment Professional Malpractice Law - Defendants Admiralty and Maritime Law Personal Injury Litigation - Defendants Product Liability Litigation - Defendants Melissa M. Lessell Commercial Litigation Ethics and Professional Responsibility Law Professional Malpractice Law - Defendants Raymond C. Lewis Insurance Law Litigation - Insurance Personal Injury Litigation - Defendants Walter P. Maestri Admiralty and Maritime Law Energy Law Personal Injury Litigation - Defendants Product Liability Litigation - Defendants Joseph L. McReynolds Appellate Practice Litigation - Construction Personal Injury Litigation - Defendants Product Liability Litigation - Defendants Professional Malpractice Law - Defendants Anne E. Medo Commercial Litigation Richard B. Montgomery III Commercial Transactions / UCC Law Litigation - Real Estate Real Estate Law Securitization and Structured Finance Law Sean P. Mount Commercial Litigation Insurance Law Litigation - Construction Litigation - Insurance Mass Tort Litigation / Class Actions - Defendants Personal Injury Litigation - Defendants Talbot M. Quinn Insurance Law Litigation - Insurance Joanne Rinardo Employment Law - Management Litigation - Labor and Employment Kermit L. Roux III Family Law Insurance Law Personal Injury Litigation - Defendants Product Liability Litigation - Defendants Brian S. Schaps Construction Law Litigation - Construction A. Wendel Stout III Litigation - Environmental Mass Tort Litigation / Class Actions - Defendants Product Liability Litigation - Defendants Kelly E. Theard Construction Law Litigation - Construction Personal Injury Litigation - Defendants Product Liability Litigation - Defendants Professional Malpractice Law - Defendants Marc J. Yellin Personal Injury Litigation - Defendants Product Liability Litigation - Defendants Gulfport, Mississippi Richard Tubertini Business Organizations (including LLCs and Partnerships) Commercial Litigation Professional Malpractice Law - Defendants R. Douglas Vaughn Health Care Law Insurance Law Litigation - Insurance Medical Malpractice Law - Defendants Personal Injury Litigation - Defendants Product Liability Litigation - Defendants Professional Malpractice Law - Defendants 2027 Best Lawyers: Ones to Watch® in America Ten Deutsch Kerrigan attorneys were recognized in the 2027 edition of Best Lawyers: Ones to Watch® in America. New Orleans, LA Gregory J. Angelico Personal Injury Litigation - Defendants   Chance Carter Personal Injury Litigation - Defendants   Colin Casciato Commercial Litigation   Peter-Raymond Graffeo Construction Law   Ethan King Personal Injury Litigation - Defendants   Jose Ruiz Insurance Law Personal Injury Litigation - Defendants Transportation Law   Justine Ware Insurance Law   Casey Wendling Professional Malpractice Law Gulfport, Mississippi Peyton Farve Insurance Law Transportation Law   Keeton Thach Insurance Law Personal Injury Litigation - Defendants Professional Malpractice Law